Perth High School

Perth High School is one of the first and largest Passivhaus secondary schools in Scotland and has been delivered as part of the Learning Estate Investment Programme (LEIP), focused on creating high-performance learning environments. 

Curved brick exterior of Perth High School beneath a cloudy sky.

Key information

Architect

NORR

Client

Perth & Kinross Council and hub East Central Scotland

Value

£80m

Year of Completion

2025

Location

Perth, Scotland

Sector

Services

A high-performance learning environment for 1,600 pupils

The school provides a high-quality environment for 1,600 pupils and 140 staff. The design supports wellbeing through good daylight, air quality, comfort, and stable temperatures while significantly reducing energy demand and carbon emissions. We supported Robertson Construction as the Passivhaus designers on the project.   

The three-storey, 15,100 m2 school has been designed to meet LEIP Band A energy targets and align with the Scottish Government’s requirements for very low operational energy use.  
 
A compact building form and envelope support Passivhaus performance, helping to reduce heat loss and improve efficiency. The building adopts a distinctive boomerang-shaped plan maximising connectivity and circulation.  

Achieving Passivhaus

We were appointed to deliver full Passivhaus services, including 2D and 3D thermal bridge modelling and PHPP modelling analysis. We were able to influence the design development and worked with Robertson Construction to provide input on the construction quality to achieve an efficient, well-performing, low-energy building.

We advised on the impact of occupancy and internal heat gains, thermal bridges, and the thermal and energy balance of U-values, windows and envelope details. We also advised on the centralised ventilation strategy to meet energy limits and the drainage design to improve thermal performance.  
 
Particular attention was paid to the areas of the design which are more unusual, such as the unique boomerang shape and deep-plan nature of the building, the overhang around the dining area, the main entrance, and the rooflights, as well as the fit-out, which affects the Primary Energy Renewable (PER) demand or the overall energy consumption of the building. The building achieved an airtightness of 0.3 ACH, which is half the required Passivhaus limit.